CASE STUDIES

HMP Lincoln – Replacement Standby Generator

Project details

Client: MOJ / Amey Community Ltd

Site: HMP Lincoln

Sector: Justice

Duration: 6 weeks onsite

Services: Mechanical and Electrical

OUR CLIENT

The Ministry of Justice is a major government department, at the heart of the justice system. They work to protect and advance the principles of justice. Their vision is to deliver a world-class justice system that works for everyone in society. The MOJ endeavour to keep their sites in top condition and so commissioned Amey Community Ltd to lead this project.

Amey Community Ltd is an infrastructure support service provider that offers facilities management. They operate across sectors such as transport, justice, defence, healthcare, and education. Amey focuses on improving public services, enhancing infrastructure efficiency, and contributing to community development through innovative solutions and sustainable practices.

Ford Mainwaring works with Amey to provide building management services for prisons across North Wales, the Midlands, and the North of England. This typically includes PPM and reactive works.

FM and Edina

THE BRIEFING

HMP Lincoln’s existing generator was reaching its end–of–life and continued maintenance would not be cost–effective.
A replacement generator would solve two problems – it would be more cost–effective than continued maintenance, and as a new generator would be more environmentally friendly.

The
existing 80,000 litre fuel tank needed to be replaced, due to heavy corrosion contaminating the fuel.


The scope of this project included the following:

  • Installation of temporary power generation & fuels
  • Decommissioning and removal of the existing redundant generator
  • Install and commission new 80,000 litre fuel tank including;
    • New double skin PLX pipework, complete with leak detection system
    • Fuel polishing
    • Fuel level control system
    • Fuel level warning system
  • Installation of new Edina, AJ Power 800 kVA standby generator package
  • We competed the LV power wiring, new link box, and connections of the control wiring from the two internal LV switch rooms within the prison
  • Completion of the necessary earthing and bonding
  • Connection of the Fire alarm installation to the site’s maintained system

    RELATED CASE STUDIES

    Amey Community Ltd – HMP

    Amey Community Ltd – HMP

    CASE STUDIES Project details Client: Amey Community Ltd Site HMP  Location: Staffordshire Services: Heating Upgrade OUR CLIENT Our client operates a secure custodial facility where reliable heating and essential building services are vital to maintaining a safe,...

    The De Ferrers Academy

    The De Ferrers Academy

    CASE STUDIES Project details Client: Affinity Learning Partnership Site De Ferrers Academy, Trent Campus Location: Burton, Staffordshire Services: HeatingOUR CLIENT Affinity Learning Partnership is a mixed multi-academy trust operating across Staffordshire and...

    Sun Academy

    Sun Academy

    CASE STUDIES Project details Client: Academy Transformation Trust Site Sun Academy Location: Newcastle-under-Lyme Services: Heating Boiler ReplacementOUR CLIENT Our client, The Academy Transformation Trust, knows that providing the very best education for their...

    Contact Us

    We’d love to chat with you.

    Fill in the form below and one of our dedicated team members will get in touch.